Important progress is being made throughout the 100 Kensington growth website, with Constructing 2—the primary residential tower—on the coronary heart of ongoing development exercise.
Constructing 2: Residential Tower Core Reaches Degree 29
Development efforts stay focused on Constructing 2, the place the raise core is sort of full, at the moment standing at stage 29. Concrete slab casting for condominium flooring has begun, with slabs at the moment in place as much as the second ground at podium stage. Metal set up has additionally progressed to stage 2, whereas the extent 4 slab has been poured and column set up is actively underway.
That is scheduled for completion for the top of summer season 2025. Cladding work is predicted to start as quickly because the fifth stage is reached.
Basement Works
Basement-level work has commenced, with development now underway on key facilities together with the automobile park, bicycle storage, and bin shops. The exterior framework of the longer term leisure centre has additionally been established. Notably, the swimming pool has been totally constructed and backfilled.
Key actions at basement stage embrace:
- Column installations
- Shear wall rebar placement
- Lightning conduction
- Slab pouring for the basement ground
- Crane base preparation for Tower Crane 3 (TC3)
Blockwork has commenced on plant rooms and substations throughout the basement stage, signalling additional progress on the important infrastructure of the event.
Metal Framework Milestone
The metal framework for Constructing 2 has been totally accomplished, marking a major structural milestone. Development crews have now shifted focus to erecting the metal framework for Buildings 3, 4, and 5.
Constructing 3
At Constructing 3, the rostrum stage is actively below development. Horizontal beams, which can assist the flooring above, are scheduled for set up within the coming weeks, alongside girder set up.
We’ll present extra updates within the subsequent quarter.
